PRINT

Bangladesh: Electricity Distribution Modernization (Rajshahi-Rangpur Divisions) Project

SUMMARY

STATUS
Proposed
MEMBER
Bangladesh
SECTOR
Energy
E&S CATEGORY
Category B
PROJECT NUMBER
000500

FINANCING

PROPOSED FUNDING AMOUNT
USD350 million
FINANCING TYPE
Sovereign

TIMELINE

CONCEPT REVIEW
June 14, 2023
APPRAISAL REVIEW/FINAL REVIEW
July 4, 2024

OBJECTIVE

To increase delivery, reliability, and efficiency of power supply in selected areas of Rajshahi and Rangpur divisions in Bangladesh.

DESCRIPTION

Bangladesh Rural Electrification Board (BREB), one of the major energy sector state-owned entities in Bangladesh, is responsible for extending electricity distribution services to the rural areas of the country. The entity, through its 80 “Palli Bidyut Samities” (PBSs) (i.e., rural electricity clusters) organized under country’s eight divisions, collectively serves nearly 75 percent of the country’s electricity consumers. Out of 80 PBSs, Rajshahi and Rangpur divisions have 21 PBSs that provide services to around 8.8 million consumers (including industrial and commercial users).

In 2022, Government of Bangladesh (GoB) announced universal access to electricity in the country. Since then, electricity demand for both domestic and industrial sectors is on the rise. Considering the rapid socio-economic and industrial development associated with the availability of electricity, BREB anticipates an increase in consumer demand for reliable electricity supply in Rajshahi and Rangpur divisions. In order to (i) cater to the expected additional demand, (ii) decongest the network, and (iii) reduce the distribution losses, BREB has initiated this project to increase the capacity and modernize the distribution network in Rajshahi and Rangpur divisions.

The following activities are planned in the project scope:

  • Component A: Installation of 84 new and augmentation of 32 existing 33/11 kilovolt (kV) substations with a total capacity of approximately 1,385 megavolt-amperes (MVA);
  • Component B: Construction and modernization of around 19,500 kilometers (km) of 33/11 kV distribution lines; and
  • Component C: Installation of six (6) River Crossing Towers, Supervisory Control and Data Acquisition (SCADA) System, and Fault Locators in certain areas

ENVIRONMENTAL AND SOCIAL INFORMATION

Applicable Policy and Categorization. AIIB's Environmental and Social Policy (ESP), including the Environment and Social Standards (ESSs) and the Environmental and Social Exclusion List (ESEL), apply to this project. ESS 1 (Environmental and Social Assessment and Management), ESS 2 (Land Acquisition and Involuntary Resettlement) and ESS 3 (Indigenous Peoples) are applicable to the environmental and social (ES) aspects of the project. The project has been assigned as Category B based on (i) the general ES impacts are limited to the project area during the implementation period, (ii) the impacts are expected to be reversible and temporary in nature and can be managed effectively using good engineering and construction practices in an operational setting.

Environmental and Social Instruments: An Environmental and Social Impact Assessment (ESIA) including an Environmental and Social Management Plan (ESMP), a Resettlement Planning Framework (RPF) and an Indigenous Peoples Planning Framework (IPPF) are being finalized by BREB. A land audit was also undertaken to identify the already purchased land for substations and to develop measures to comply with AIIB’s ESP.

Environment Aspects. Potential key environmental risks and impacts of project components have been identified. For Component A, key considerations for the augmentation activities for existing substations includes, but is not limited to: historical use of polychlorinated biphenyls (PCB) containing transformers; transformer oil storage; historical monitoring; disposal of transformers; fire safety; and community health and safety. On the other hand, for new substations, this includes but are not limited to: usage of PCB-free transformers; oil leakage protection; drainage and wastewater management; community health and safety; and hazardous materials and waste management. For Component B, this includes: right-of-way and maintenance; community health and safety; avian and bat collisions and electrocutions; and chemically-treated wooden poles. For Component C, key considerations include: temporary land use restrictions and loss of standing crops and trees; and navigation safety. Key mitigation measures following the mitigation hierarchy and in accordance with good international industry practices (GIIP) are included in the ESMP.

Social and Gender Aspects. The project aims to enhance the distribution capacity and improve the reliability and quality of electricity supply in Rajshahi and Rangpur divisions. Components A and B will require land for the construction of proposed substations and for securing the right-of-way for distribution lines, and the client will ensure its availability through direct purchase. PBSs are mainly responsible for the land purchase, under the supervision of the BREB. For the 32 existing substations, the land is readily available and owned by the respective PBSs. The PBSs have also purchased 4.27 Hectare (Ha) of land for 23 new substations, and a land audit is ongoing to ascertain compliance with AIIBs’ ESP. The PBSs are in negotiation to purchase another 11.65 Ha of land for the remaining 61 new substations, and a RPF has been prepared to guide the preparation of site-specific Resettlement Plans (RPs). In addition, a Gender Action Plan (GAP) developed for the project and to be implemented by BREB together with its PBSs will contribute to bridging the inequalities that exist between women and men in Bangladesh. The GAP specifically targets the female employees of BREB and PBSs and their female electricity consumers in Rajshahi and Rangpur divisions.

Occupational Health and Safety, Labor and Employment Conditions. BREB has a Standard Operating Procedure (SOP) for substation or distribution network operation, inspection and maintenance; SOP for emergency response procedures and management; and an SOP for training in safety working procedures. The project workforce is expected to be comprised of project-contracted workers, primary supplier workers, and potentially migrant workers. Key risks and impacts include live power lines, life and fire safety, working at height, and chemical exposure, among others. The ESMP also includes measures to mitigate risks and impacts on occupational health and safety and labor and working conditions. The implementation of the ESMP requirements and compliance with the relevant country laws and regulations, BREB’s ES standards, and GIIP will be reflected in relevant bidding documents, agreement and contracts with primary suppliers and contractors.

Stakeholder Engagement, Consultation and Information Disclosure. The ESIA, including the ESMP, outlines a set of broad public consultation activities and information dissemination to affected people, including public meetings in project areas, focus group discussions, and information awareness campaigns. This will be undertaken early and throughout project preparation and implementation. Also, the PBSs will set up and manage project information centers, responsible for disseminating information to stakeholders. Information will be made available in English and Bengali. The ESIA, which includes the ESMP, the RPF and IPPF, in English, and the executive summaries in Bengali, will be disclosed timely online on both the AIIB and BREB websites.

Project Grievance Redress Mechanism. BREB will establish a project-level grievance redress mechanism (GRM) in accordance with the requirements of AIIB’s ESP for the project. The GRM will include a procedure to receive and facilitate the resolution of project-affected people’s concerns and complaints about any irregularities. The GRM will operate at three levels: (i) PBS field officers will receive and respond to grievances from project affected people, and seek to resolve minor grievances; (ii) if the grievance cannot be resolved at the field level, it will be referred to a focal point at Project Management Unit (PMU); and (iii) if the matter cannot be resolved at the PMU grievance committee level, the matter will be referred to a Grievance Redress Committee (GRC) headed by the Chief Engineer (Project) at BREB. All ES information, including the GRM at the project level and AIIB’s Project-affected People’s Mechanism (PPM) will be posted on BREB website in English and Bengali. In addition to the above, a commensurate mechanism will be made available at the contractor level for workers’ grievances.

Monitoring and Supervision arrangements: The PMU will be fully responsible for monitoring the implementation of the project and is expected to prepare progress monitoring reports semi-annually based on agreed format highlighting progress on ESMP implementation, which will be shared with AIIB. During the project implementation, the Bank will carry out missions to monitor progress and may conduct additional field visits as required during the initial years.

PROJECT TEAM LEADER

Asian Infrastructure Investment Bank

Raqib Ahmed Chowdhury

Investment Officer

raqib.chowdhury@aiib.org

BORROWER

People’s Republic of Bangladesh

Mirana Mahrukh

Additional Secretary & Wing Chief (Asia, JEC, F&F), Economic Relations Division (ERD), Ministry of Finance

wingchief08@erd.gov.bd

IMPLEMENTING ENTITY

Bangladesh Rural Electrification Board (BREB)

Ajay Kumar Chakraborty

Chairman

chairman@reb.gov.bd

Home Projects Project Summary Project List Project Details Electricity Distribution Modernization (Rajshahi-Rangpur Divisions) Project